Note:
These all articles are dedicated to my teachers, my seniors, colleagues, internet bloggers, online technical material, reference books from where I learned all these. There are chances that the material presented here is duplicated somewhere on the web. If anything is replicated anywhere, I sincerely give proper credits to the contributor.
All the Cost Calculations for PMP exam are related to each other and tightly linked. When you get a bunch of data in the question, you start getting confused. Sometimes you don’t even need to calculate anything and answer is given directly in the question. All that jargon AC, PV, EV blah, blah is given there to confuse the exam taker.
The
only trick here is just know basics. Understand the basic definition of each of
the cost related term which may appear in the question and you can answer those
questions perfectly correct in the exam.
So
are you ready? We will start with the easiest thing ever, which you also
encounter in daily life i.e. Actual Cost. Isn’t it easy? The amount which cost
you to do anything....
Anyway,
let’s start with all those definitions with the examples calculation.
- Actual Cost (AC) or Actual Cost of Work Performed (ACWP)In simple terms, “How much we have spent till today?”. This “Today” is called the Data Date as we are measuring the performance on this date.In other words, Actual Cost (AC) is the actual costs incurred by the project as of a certain point in time.There is no as such formula. You need to look at how much we have spent till the date in question.Example: Anil has budgeted $1.5 million for his construction project. The project has spent $300,000 on foundation and wall construction, $30,000 Electricity installation and, $13,000 on team management activities. What is the AC of the project?Answer: See how much project has spent till date.It is 300000+30000+13000 = $343000.No need to look at the Budget. Just concentrate on what has been spent.
- Budget at Completion (BAC)It is the estimated cost when the project will be completed. Generally it is determined when the project is started (Remember “Determine Budget” process). Most of the times, it is given in the question unless the question is not intentionally made to create confusion.So, simply this is the money you need to complete the project.Example: Sujit is the project manager on a project to develop a public park. The materials are estimated to cost $200,000. The labor cost is estimated at $55,000. There are other costs which are directly attributed to the project and are estimated at $25,000. Maintenance cost of the park (including the salary of the gardener) is estimated at $40,000. Find the BAC?Answer: See how much the project will cost at completion.200000+55000+25000 = $280000Note: Ongoing operation and maintenance costs are not part of the project, so we have not included them in our Budget.
- Planned Value (PV) or Budgeted Cost of Work Scheduled (BCWS)
This is the estimated value of work
for a specified time period. It means how much budget (out of the total) you
have planned for that particular period when you are measuring your project
performance.
Example: Shampi is the project manager on a
project for developing and E-Commerce portal. The project is expected to last 12
months. The total Budget for the project is $200000. After 5 months projects
has planned for 40% work to be completed. What is the Planned Value (PV)?
Answer: After 5 months project is
planned to be completed 40%, and the total budget is $200000. So our Planned
Value is 40% of total budget. And that should be
40%
of 200000 = (40/100)*200000 = $80000
Warning: Sometime it is not mentioned that how
much you have planned. For example in above example, if it is not given that
after 5 months project will be completed 40% then there is no way you can find
the PV as you do not know what is planned in those 5 months. Exam takers assume
the budget is divided equally for each month and they do the calculation
accordingly. Never do that because you do not know what is planned.
4. Earned Value (EV) or Budgeted Cost of
Work Performed (BCWP)
This the estimated value of actual
work performed as of today (this “as of today” is also
called Data Date).
Note the difference between PV and EV.
PV was what you have planned and EV is what you have achieved.
What does it mean?
If the project is terminated today
itself, EV will show you the value project achieved. If you see some question
where it talks about Post Mortem Analysis of a project and give you PV, EV and
AC, and these values shows you project
is behind schedule and under budget (how, we will see later) please assume the
project was terminated.
Earned Value (EV) is used to calculate
Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI),
Cost Performance Index (CPI) and To-Complete Performance Index (TCPI). How, we
will see in this article only, but a bit later.
Let’s modify the above example to make
it easy.
Example: Shampi is the project manager on a
project for developing and E-Commerce portal. The project is expected to last 12
months. The total Budget for the project is $200000. After 5 months projects
has planned for 40% work to be completed. She was able to complete half of the
project. What is the Earned Value (EV)?
Answer: Now from the above example of PV, we
know that the PV is $80000 as we have planned for 40% of the work of $200000.
Since we have achieved half of the
work (50%), the earned value will be:
EV
= (50/100)*200000 = $100000
It shows that the project has achieved
more than what was planned. Good for the project, right?
Note: Please note that ACWP, BCWS and BCWP
are the terms used previously by the exam for AC, PV and EV. You do not need to
remember these terms as the question states both the terms.
This concludes the Part-1 of “Mastering
the Earned Value Calculations for PMP Exam”. In Part-2, we will master the
calculations related to Project Performance i.e. Cost Variance (CV), Schedule
Variance (SV), Cost Performance Index (CPI) and Schedule Performance Index
(SPI).
No comments:
Post a Comment