Note:
These all articles are dedicated to my teachers, my seniors, colleagues, internet bloggers, online technical material, reference books from where I learned all these. There are chances that the material presented here is duplicated somewhere on the web. If anything is replicated anywhere, I sincerely give proper credits to the contributor.
In Part-3 of “Mastering the Earned
Value Calculations for PMP Exam”, we have studied about the Project Estimations
mostly EAC which keeps changing as the scenario changes.
Now, in Part-4 of we will study one
very important index of project performance which is To Complete Performance
Index (TCPI) which also changes with the scenario. We will master all the
scenarios related to that.
To-Complete Performance Index (TCPI)
To-Complete Performance Index (TCPI)
It is again an estimate which is
calculated basically to know what performance is need to achieve the project
goal. To-Complete Performance Index (TCPI) is an estimate of the performance
needed to achieve a goal. It is clear from the name itself, To Complete
Performance Index.
For example, if you are driving a car
from New Delhi to Dehradun and you have a goal to reach Dehradun by 11:00 AM.
Dehradun is 300 kms from New Delhi. You start at 6 AM and driving at 55 kms/hr
and its 10:00AM now.
So what does it mean you have to cover
80 kms in an hours now. So your TCPI will
Formulae
for TCPI
Again there are more than one formulae
for TCPI and it changes with the scenario. One formula is based on the BAC; the
other is based on EAC.
But what actually TCPI means. Ideally
it is ration of Work Remaining to the Funds remaining.
So in simple words you can write:
TCPI = Work Remaining /
Funds Remaining.
It means if TCPI >1, it is not good
for project because it shows either the fund remaining are less than the value
of the work remaining or Work remaining is greater than the funds remaining
(either way is same)
Can you guess how you can calculate
the work remaining and funds remaining?
Work remaining is the difference of
total budget and what the work you have achieved, right?
So
Work Remaining = BAC – EV
(makes sense?)
And what are the funds
remaining?
This is a question to
think. It can change based on the scenario.
Well,
- If you fundamentals estimates are not flawed yet (original budget is still valid), then it will be the difference of Original Budget and Actual Costs.
Funds Remaining = BAC – AC
- If you need to calculate a new budget (EAC), then it will the difference of Estimate at Completion and Actual Costs.
Funds Remaining = EAC – AC
So the
formula of TCPI will be changed accordingly
Scenario 1 – Original Budget (BAC) is valid
We know that BAC is an estimate of the
project cost that you created at the start of the project. If this estimate is
still valid, use this formula:
To-Complete Performance Index = Work
Remaining / Funds Remaining.
From the discussion above
TCPI (When BAC is valid)
= BAC – EV / BAC – AC
Example: The project is due to be completed in two months. At the start of the
project, it was estimated that the project would cost $100,000 to complete. Till
date project has spent $60,000. As per the estimation project has completed the
work of worth $70,000. There is nothing bad with the project and it is estimated
the project will be completed on time and on budget. What is the To-Complete
Performance Index?
Answer: Now if we read the question carefully, project
will be completed on budget and there is no new estimate (EAC) needed. We can
safely assume that BAC is still valid.
Now see the
data presented in question:
BAC = $100000,
AC = $60000, EV = $70000
Since the BAC is still valid
TCPI = BAC – EV / BAC –
AC
TCPI = (100000-70000) / (100000-60000)
= 30000/40000 = 0.75
TCPI < 1, so it is good for
project.
Scenario 2 – Original Budget (BAC) is flawed and you need a new estimation (EAC)
We know that BAC is an estimate of the
project cost that you created at the start of the project. If this estimate is not
valid now, you need a new estimate and that is your EAC. Then, use this
formula:
To-Complete Performance Index = Work
Remaining / Funds Remaining.
From the discussion above
TCPI (When BAC is not valid
anymore) = BAC – EV / EAC – AC
Let’s modify the above example and
calculate the TCPI.
Example: The project is due to be completed in two months. At the start of the
project, it was estimated that the project would cost $100,000 to complete. Till
date project has spent $80,000. As per the estimation project has completed the
work of worth $40,000. There has been a major quality issue in the project and
new estimated are needed. Now it is estimated that new costs will be 130,000 at
the completion of the project. What is the To-Complete Performance Index?
Answer: It is very clear from the question
that original budget is flawed and no more valid. New costs are estimated at
project completion (EAC). Since BAC is flawed, we will not use this in our
calculation. BAC is just presented to create confusion or you can say, to make
the question more complete.
Now see the
data presented in question:
BAC = $100000,
EAC = $130000, AC = $80000, EV = $40000
Since the BAC is no more valid and EAC
is in place now
TCPI = BAC – EV / EAC –
AC
= (100000-40000)/(130000-80000) =
60000/50000 = 1.2
TCPI > 1, so it is not good for
project.
Note: Please note that “Work Remaining” is
always BAC-EV doesn’t matter what the scenario is. Because work remaining is
always measured from Original Budget and Earned value (Check other parts of “Mastering
Earned Value Calculations”)
No comments:
Post a Comment